Progress in the construction of Comfort Residence – Malinova Dolina II for October 2026.
10.11.2026, from the Stonehard Team
At the beginning of autumn, the construction of Comfort Residence – Malinova Dolina 2 is entering the final stages of the project implementation. Current activities focus on finishing the common areas, installing equipment, and shaping the outdoor spaces.
The project is being carried out by the construction-investment company TASKOV & STOYANOV, and the construction works are performed by Elite Building Company. The completion of the building is planned for end of 2026.
The project includes a total of 40 apartments, 41 underground parking spaces, and 10 above-ground parking spaces. Currently, a limited number of two-bedroom and three-bedroom apartments with functional layouts are available on the market.
Construction continues according to the pre-planned and approved linear schedules, with the following construction and installation works completed in October:
The following construction and installation works were completed last month:
• Work on the exterior railings on the terraces continued;
• Installation of entrance doors began;
• Installation of gypsum board ceilings in the common areas was completed;
• Elevator installation was completed;
• Installation of the double floor on the attic level was completed.
The following works are planned for the next month:
• Application of the final plaster in the common areas will begin;
• Polished concrete will be laid in the underground garages;
• Installation of entrance doors will be completed;
• Work on the vertical landscaping around the building will continue;
• Installation of the exterior railings on the terraces will be completed.
To arrange a viewing or if you need additional information, please contact the responsible consultant Lyubin Chakov at tel.: +359 882 817 565 or visit our website.



The construction of Comfort Residence – Malinova Dolina 2 is progressing according to the planned schedule. In September, the installation of elevators and drywall ceilings in the common areas was completed, and the project is entering the final stages of implementation.